If you have access to more than one Org in SnapLogic, you can migrate Projects from one Org to another by creating a copy of the Project. The original Project remains unchanged.

To migrate a Project:

  1. In SnapLogic Manager, select the target Project and clickto display the dropdown menu, then click Migrate to open the Migrate project dialog.

  2. Select your Org from the Org to migrate to selector, and then select the Project Space from the Project Space to selector. 


  3. Click Choose asset types to migrate and review the following guidelines:
  4. Select the assets you want to migrate and click Migrate. After making your selection, a notification appears indicating that the migration has started. When the migration is complete, Manager displays a second notification.

If the Project references files in a /shared directory, copies of those files are also migrated if they do not already exist in the relative /shared folder in the Org to which you are migrating Assets.