  1. Click Manager.

  2. From the left navigation, select the Project Space to which the Ultra Task belongs.

  3. Select the Tasks tab.

  4. Click the Ultra Task name. The Update Task dialog displays:

...

Changing the Run Policy

When you create an Ultra Task, Ultra is set as the Run Policy by default. If you change the Run Policy setting to Triggered or Scheduled, you must re-configure the Task.

...

  1. In Manager, navigate to the Ultra Task and select Details from the dropdown menu:

  2. On the Task Details page, view execution statistics by clicking Run Details:

    Image RemovedImage Added