Comment: 4.30.1 IIP Redesign changes

You may want to move pipelines can move Pipelines from one project to another.

Info
titleIIP Redesign

In September 2022 release, the SnapLogic IIP redesign declutters the Designer toolbar by removing the Move icon and its functionality. You can still move your Pipelines from one project to another in Manager.


Excerpt

To move a pipeline Pipeline to a different project:

  1. In Manager,
 select
  1. navigate to your project.
  2. Select the checkbox next to the
pipeline
  1. Pipeline name
and click Move.In Designer, open the pipeline to move and click Move pipeline on the toolbar. You can filter the destination list by entering the project name in the text box
  1. Click Move.
Info
titleReferences in Pipelines

When moving a pipeline Pipeline that contains references, the references are treated as follows:

  • If the reference is to an asset Asset in the Shared shared folder, leave the reference as is.
  • If the reference is to an asset Asset in another project from the target project:
    • If the reference to a file is absolute, keep it.
    • If there is an asset Asset with the same label in the destination project, reference the asset Asset in the destination project.
    • If not and there is an asset Asset with the same label in the shared project, reference the asset Asset in the shared project.
    • If the asset Asset doesn't exist with that label, blank out the field.
  • When moving a pipeline with one or more nested pipelines, move the nested pipelines before moving the parent pipeline.



...