To move a Pipeline to a different project:

  1. In Manager, navigate to your project.
  2. Select the checkbox next to the Pipeline name.
  3. Click.
Info
titleReferences in Pipelines

When moving a Pipeline that contains references, you should handle the references as follows:

  • If the reference is to an Asset in the shared folder, leave the reference as is.
  • If the reference is to an Asset in a different project from the target project:
    • If the reference to a file is absolute, keep it.
    • If there is an Asset with the same label in the destination project, reference the Asset in the destination project.
    • If there is no Asset with the same label in the destination project but there is an Asset with the same label in the shared project, reference the Asset in the shared project.
    • If the Asset doesn't exist with the same label, blank out the field.

When moving a Pipeline with one or more nested Pipelines, move the nested Pipeline before moving the parent Pipeline.